9th - 13th March 2009
Thankfully a much more productive week. Jings, crivens and help ma boab!
As far as the plumbing goes, all the radiators and pipes have been fixed and the soil pipes and drain pipes are in too.
Tuesday was a bit frantic because the sparkies arrived on site as well and put in many of the lights and the various switches.
And we now have garage doors!!
Methinks the floor may be ready to be poured in next week.
View of the cleared bank from the front door
Martin the plumber's showing who's the boss.
Spaghetti Junction in the airing cupboard
Week 34
Week 33
Week 32
Week 31
Week 30
Week 29
Week 27
Week 26
Week 25
Week 24
Week 23
Week 22
Week 21
Week 20
Home
Drainpipe - what drainpipe?
Abby inspects the garage plasterwork
I guess the clear-up will start next week
No comments:
Post a Comment